1. Check the condition of the pump before installation.
2. The pump should be installed as close as possible to the water source.
3. There are two ways to install the pump and the base, one is the rigid connection directly installed on the cement foundation and the other is the flexible connection with JGD type shock absorber.
4. Direct installation of the pump can be placed on the basis of padding 30 to 40 mm (prepared for filling with grout), and then calibrated and put on anchor bolts, filling cement mortar, after 3 to 5 days of cement dry up, Correct, until the cement is completely dry, tighten the anchor bolt.
5. Install the pipeline, the inlet and outlet pipes should have their own support, should not make the pump flange to withstand excessive pipeline weight.
6. Pump for suction occasion, the inlet pipe should be equipped with the end of the valve, and the import and export pipelines should not have too many corners, while no leakage, leakage phenomenon exists.
7. In the inlet pipe is best equipped with filters to prevent impurities from entering the impeller. The effective area of ​​the filter should be 3 ~ 4 times the area of ​​the inlet pipe to ensure the free flow of liquid.
8. In order to maintain and use convenient and safe, a regulating valve is installed on the inlet and outlet of the pump, and a pressure gauge is installed near the outlet of the pump to ensure the operation within the rated range to ensure the normal operation and service life of the pump.
9. If you need to expand the diameter of imports, please use eccentric reducer pipe joints.
Unit start, run and stop
First, start
1. pump group for suction occasion, that is, when the import is negative pressure, the pipeline should be filled with water or water pump, the water filled the pump and the inlet pipe, pay attention to the import pipeline must be sealed, there must be no Leakage exists. (Do not start without water before starting, you must first water, after the start)
2. Rotate the rotor several turns by hand to lubricate the bearing and check whether the impeller and the seal ring in the pump are rubbing against each other. If the rotor does not move, it should not be started until the cause of the fault is found.
3. Close the gate valve and pressure gauge cock on the outlet tube to reduce the starting current.
4. Start the test, the motor should be turned and the arrow on the pump point to the same, open the meter cock.
5. When the rotor reaches normal operation, the pressure gauge shows pressure, gradually open the outlet gate valve, adjust to the desired conditions.
Second, work
1. Pumps in operation, we must observe the instrument readings, try to make the pump in the nameplate flow near the head work to prevent large-flow operation.
2. Regularly check the motor current value should not exceed the rated current.
3. Pump bearing temperature shall not exceed 75 ℃, and shall not exceed the outside temperature of 35 ℃.
4. The pump pack should be loosened at the beginning of operation Gland, when the expansion of graphite or filler is fully expanded and then adjusted to the appropriate level.
5. Wear parts too large wear and tear should be promptly replaced.
6. Found anomalies, stop immediately check the reasons.
Third, downtime
1. Close the gate valve on the outlet pipe and close the vacuum gauge cock.
2. Stop the motor, then close the pressure gauge cock.
3. If the winter cold season, the pump liquid should be exhausted, so as to avoid cracking.
4. Long-term stop using the pump should be disassembled, cleaned and oiled, safekeeping.